Ignoring Saturdays and Sundays

Hi all,

I created a Process and I would like to put a Wait event with a duration of 3 days but I would like to ignore the week-end in this 3 days.

If the wait event start the Friday I would like that it stops wednesday.

Do you have a solution to do that?

Thank you for your help.

Best regards,

Parents Reply Children
  • HiJeff Bickart,

    A process definition is triggered by a save event, and calculated fields are updated during save events. Therefore, the same mechanism that triggers a process of this definition automatically updates the calculated field, which is why it is essential that the gateway evaluating the calculated field occurs on the same day the process is triggered.

    You are accurate that there is not a stock scheduler that updates calculated fields in Sugar regular, but this scenario does not appear to call for that.